Critical path_____________?
A. is always longest
B. is always shortest
C. may be longest
D. may be shortest
Which of the following is a weakness of bar chart ?
A. interdependencies of activities
B. project progress
C. uncertainties
D. all of the above
Which of the following is not a PERT event ?
A. site investigation started
B. sessional work completed
C. bus starts from Jaipur
D. class is being attended
The area under the Beta – distribution curve is divided into two equal parts by_______________?
A. most likely time
B. optimistic time
C. pessimistic time
D. expected time
Which of the following does not represent an activity?
A. site located
B. foundation is being dug
C. the office area is being cleaned
D. the invitations are being sent
Latest start of an activity is always________________?
A. greater than or equal to latest event time of preceding node
B. less than or equal to latest event time of preceding node
C. equal to latest event time of preceding node
D. less than latest event time of preceding node